Project status report format: a weekly template you can copy, and how to fill it
Project status report format: a weekly template you can copy, and how to fill
it A good project status report fits on one screen and answers five questions:
how is the project doing, what got done, what is next, what could go wrong,
and what do you need from the reader. The template below has exactly those
five sections. Copy it, fill it in once a week, and post it where your
stakeholders already read. The template Copy this into a doc, a Slack message
or an email. Replace the words in brackets. Project: [name] | Week of: [date
range] | Owner: [name] 1\. Summary Status: Green, Amber or Red, and one
sentence on why. Next milestone: [name], [date], on track, at risk or late.
2\. Done this week [outcome], [link to ticket] [outcome], [link to ticket] 3\.
Next week [planned outcome], [owner] [planned outcome], [owner] 4\. Risks and
blockers [risk]: impact [what happens], owner [name], mitigation [what you are
doing] 5\. Asks [decision or help needed], from [name], by [date] How to fill
each section Summary. Write the status last, but put it first. Use green when
you expect to hit the next milestone with no help, amber when you will hit it
only if something changes, and red when you will miss it without a decision
from someone else. Add one sentence of reason. If you cannot write the
sentence, the status is not clear yet. Done this week. List outcomes, not
activity. "Checkout redesign shipped to 10% of users" beats "worked on
checkout". Link each item to its ticket so readers can click through instead
of asking. Next week. Three to five items, each with an owner. If an item was
in last week's "Next week" and is not in "Done", say why in the risks section.
Risks and blockers. Name the impact in plain terms, an owner, and what you are
doing about it. A risk with no owner is a complaint. Asks. The most useful
section and the one most often left out. Each ask names a person and a date.
If you have no asks, write "None" so readers know you looked. Keep the same
sections in the same order every week. Readers learn where to look, and a
change in status stands out. Where the facts come from Most of "Done" and
"Next" is already in your tracker. In Jira, a JQL filter such as project = ABC
AND resolved >= -7d lists last week's finished work, and sprint in
openSprints() lists what is in the current sprint. In Linear, filter a project
or the current cycle by status. Paste the results into the template and write
the summary yourself. Do it with Kipwise Agent If your issues live in Linear
or Jira, Kipwise Agent can draft the report from them. It is an AI agent in
Slack that reads your Linear or Jira issues as you, using your own connected
account, and it can run a request on a schedule. Try this in the channel where
the report belongs: "@Kipwise Agent every Friday at 16:00, draft this week's
status report for the Linear project Website Relaunch with these sections:
summary with status, done this week, next week, risks and blockers, asks. Link
each issue." For Jira, name the project or sprint: "...from the current sprint
in Jira project WEB". What happens: At 16:00 on Friday it posts "Scheduled for
@you" with your request and answers in that thread, as you. It lists the
issues in the project or current cycle (Linear) or searches with JQL (Jira),
opens the ones it needs for detail, and fills your template with links to each
issue. It is a draft. You read it, fix the status and the asks, and post it.
The summary colour and the asks are judgment calls it cannot make for you.
Limits to know: It only reports what it fetched. If your team does not update
issue status, the report will show that, not what really happened. Scheduled
requests use your Slack time zone, can repeat at most every 10 minutes, and
you can have 20 active per person. See Scheduled requests and reminders . You
need to connect Linear or Jira first: Connect your tools to Kipwise Agent . A
draft that only reads issues does not change anything in Linear or Jira. If
you later ask it to update an issue, it shows an approval card first. See What
Kipwise Agent needs your approval for . Questions How long should a weekly
status report be? One screen. If a section needs scrolling, move the detail to
a linked doc and keep a one-line summary here. What is the difference between
a status report and a standup? A standup is spoken, daily, and for the team. A
status report is written, weekly, and for people outside the daily work who
need to decide or stay informed. Should I use RAG colours? Yes, if you define
them. Green, amber and red mean nothing until the team agrees what each one
commits you to, as in the summary step above.